Niagara Tunnel Project
Encyclopedia
The Niagara Tunnel Project is the most recent in a series of additions to the Sir Adam Beck
Sir Adam Beck Hydroelectric Power Stations
Sir Adam Beck Hydroelectric Power Stations are two hydroelectric power stations in Niagara Falls, Ontario, Canada. The stations divert water from the Niagara and Welland Rivers above the falls which is then released into the lower portion of the river, and together produce up to 1,926 MW.Adam Beck...

 hydroelectric generation complex in Niagara Falls, Ontario
Niagara Falls, Ontario
Niagara Falls is a Canadian city on the Niagara River in the Golden Horseshoe region of Southern Ontario. The municipality was incorporated on June 12, 1903...

, Canada
Canada
Canada is a North American country consisting of ten provinces and three territories. Located in the northern part of the continent, it extends from the Atlantic Ocean in the east to the Pacific Ocean in the west, and northward into the Arctic Ocean...

.

Background

First constructed in 1922, the initial Sir Adam Beck power generating station, now abbreviated as SAB 1, derived its water supply from a canal connected to the Welland River
Welland River
The Welland River is a river in the Niagara Region of southern Ontario which flows from its headwaters south of Hamilton, Ontario to empty into the Niagara River near the city of Niagara Falls, Ontario. It drains an area of 880 km²....

. However, due to increased power demand in later years, a second generating station, known as SAB 2, was constructed in 1954. It derives its water supply from two diversion tunnels, each about 9 kilometres in length. In 1958, a reservoir and the SAB Pump were constructed in order to make better use of available water by storing it during periods of low demand and using it in periods of greater demand in order to maximize the efficiency of the stations in regards to electricity supply and demand.

Between 1996 and 2005, Ontario Power Generation
Ontario Power Generation
Ontario Power Generation is a public company wholly owned by the Government of Ontario. OPG is responsible for approximately 70% of the electricity generation in the Province of Ontario, Canada. Sources of electricity include nuclear, hydroelectric, solar, wind, and fossil fuel...

, which owns and operates the SAB complex, completed a series of major upgrades at the SAB 2 plant, increasing its potential generating capacity by 194 megawatts. Water delivered by the new Niagara Tunnel will complement this SAB 2 upgrade, and overall will increase the efficient use of the power of the Niagara River
Niagara River
The Niagara River flows north from Lake Erie to Lake Ontario. It forms part of the border between the Province of Ontario in Canada and New York State in the United States. There are differing theories as to the origin of the name of the river...

.

Construction

The Niagara Tunnel is being dug using a Tunnel Boring Machine
Tunnel boring machine
A tunnel boring machine also known as a "mole", is a machine used to excavate tunnels with a circular cross section through a variety of soil and rock strata. They can bore through anything from hard rock to sand. Tunnel diameters can range from a metre to almost 16 metres to date...

, or TBM affectionately named "Big Becky" in honour of Sir Adam Beck. The machine will bore a hole about 10.4 kilometers long and about 14.4 meters in diameter under the City of Niagara Falls from the Niagara River to the SAB complex. This massive undertaking will create about 1.6 million cubic meters of rock and debris. The TBM operates about 140 meters below the ground, and as a result, the vibrations from the machine will not be felt on the surface. The design-build contractor for the project is Strabag AG
Strabag
Strabag is a European construction company based in Villach, with its headquarters in Vienna, Austria). It is the largest construction company in Austria and one of the largest construction companies in Europe...

, a large construction group with extensive experience in large tunnel construction.
Due to slower than projected boring progress caused by constant tunnel roof over-break, the project completion date has been extended to at least 2013 with a total projected cost of $1.6B.